Environmental impact assessment documents for a construction project in Georgia
    EIA & permits

    Georgia's Environmental Assessment Code: Screening, Scoping and EIA Explained

    By Tornike Asatiani
    8 min read

    Georgia's Environmental Assessment Code decides which projects need an environmental impact assessment (EIA) and how an environmental decision is issued. The core rule: activities in Annex I always need an EIA, while activities in Annex II first go through screening. Either way, the activity may start only after the environmental decision is issued (Article 5).

    This guide walks through the procedure step by step: who files what, how many days each stage takes and which authority decides. All day-counts come from the consolidated text of the Code on matsne.gov.ge, checked on 22 November 2026.

    What the Environmental Assessment Code covers

    The Parliament of Georgia adopted the Code on 1 June 2017 (No. 890-IIს). It sets out three procedures:

    • Environmental impact assessment (EIA) for specific projects such as plants, power stations, roads and waste facilities;
    • Strategic environmental assessment (SEA) for state and municipal strategic documents (Chapter III, Articles 18–29);
    • Transboundary assessment where a project in Georgia may affect another country, or the other way round (Chapter V, Articles 37–41).

    For companies, the EIA procedure is the one that matters, so most of this article is about it.

    Who decides: the Agency, not the Ministry

    You will often read that an EIA is "approved by the Ministry". Under the current text that is not accurate. Screening decisions, scoping opinions and environmental decisions are issued by the Agency, meaning the National Environmental Agency, a legal entity of public law within the Ministry of Environmental Protection and Agriculture (Article 3).

    The Ministry sets policy and takes part in strategic and transboundary assessment, but decisions on individual projects sit with the Agency. In practice this matters: applications go to the Agency, and statutory deadlines run from registration there.

    Annex I and Annex II: does your project need an EIA?

    The Code has two annexes. Annex I activities always need an EIA. Annex II activities go through screening, and the Agency decides whether an EIA is needed.

    Examples from the annexes (see the Code for the full lists):

    AnnexActivityThreshold
    I (EIA mandatory)Thermal power plant or other combustion unit10 MW or more
    IHydropower plant5 MW or more
    IRecovery or disposal of hazardous wasteMore than 10 t per year
    IRecovery or disposal of non-hazardous wasteMore than 100 t per year
    IConstruction of a road of international or national importanceNo threshold
    IReconstruction of such a roadSection of 5 km or more
    II (screening)Combustion unit generating electricity2 MW or more
    IIConversion of agricultural land to non-agricultural use10 ha or more
    IIHousing for large livestock500 head or more
    IICommercial extraction of groundwaterMore than 100,000 m³ per year

    Two practical points. First, Annex II covers not only new activities but also changes to the operating conditions of existing ones. Second, if you are close to a threshold, filing a screening application is usually safer than assuming the procedure does not apply.

    Screening (Annex II activities)

    Screening is how the Agency decides whether an Annex II activity needs a full EIA (Article 7). The Code asks the operator to file the screening application "as early as possible".

    What the application contains: a short description of the planned activity, its characteristics and location (with GIS coordinates and a shapefile), and the likely nature of its impact.

    Timeline:

    1. The Agency publishes the application within 3 days of registration.
    2. The public can comment within 7 days of publication.
    3. The screening decision is issued no earlier than day 10 and no later than day 15 after registration.
    4. The applicant is notified within 1 day, and the decision is published within 5 days.

    The screening decision is a public document, so its reasoning about your project will be visible to everyone. Keep the information in the application accurate and consistent.

    If the Agency decides no EIA is needed, the activity proceeds on the basis of that decision. If an EIA is needed, the next step is scoping.

    Scoping: agreeing what the EIA must study

    Scoping fixes in advance what the EIA report has to cover. The operator files a scoping application and a scoping report with the Agency (Articles 8–9).

    • The Agency publishes the application within 5 days of registration.
    • The public can comment within 15 days of publication.
    • A public hearing is held between day 10 and day 15 after publication.
    • The scoping opinion is issued between day 26 and day 30 after registration.

    The scoping opinion lapses if no environmental decision is obtained on its basis within 5 years. Keep that in mind if a project stalls.

    Expert Support

    Unsure about your compliance obligations?

    Our environmental consultants can assess your situation and provide a clear action plan.

    What the EIA report must contain

    Article 10 sets the content of the EIA report. In short, it must include:

    • a description of the activity and its site, and the baseline state of the environment;
    • alternatives, including the "zero" (no-project) alternative;
    • expected significant impacts on human health, biodiversity, water, air, soil, climate, landscape and cultural heritage;
    • construction and operation impacts, emissions, waste and cumulative effects;
    • a plan of measures to prevent, mitigate and compensate impacts, and accident response;
    • irreversible impacts and site restoration after the activity ends;
    • responses to public comments, methodology, data sources and a non-technical summary.

    The mitigation plan often becomes the basis of an environmental management plan (EMP/ESMP), which lenders such as international financial institutions usually require as a separate document.

    Public hearing and the environmental decision

    With the EIA report, the operator files an application for an environmental decision (Articles 11–12). The EIA fee is 500 GEL (Article 11(5)).

    StageDeadline
    Application publishedWithin 5 days of registration
    Public comments40 days from publication
    Public hearingDay 25–30 after publication (notice at least 20 days before)
    Environmental decisionDay 85–90 after registration
    Accelerated procedureDay 51–55 after registration (additional fee)

    The Agency sets up an expert commission to review the report. The decision states the location and type of activity, conditions for the construction, operation and post-operation phases and, where needed, the scope and frequency of post-project analysis (Article 13).

    The environmental decision has no expiry date, but the Agency declares it void if the activity has not started within 7 years.

    What happens if you breach the decision's conditions

    The decision is not the end of the story. The Code sets separate liability for failing to meet the conditions of an environmental decision (Article 46). Non-compliance is fined, the sanction increases if the breach is not fixed by the deadline set, and repeated non-compliance can lead to the decision being revoked.

    That is why it pays to build a conditions register as soon as the decision is issued: what has to be done, by whom and by when.

    Common mistakes we see in practice

    • Starting preparatory works too early. Site clearing or earthworks are often treated as part of the activity. Without a decision, they create risk.
    • Not assessing changes. A new production line or higher capacity at an existing plant is a change to operating conditions and may need screening, even if the original activity did not.
    • Treating the public hearing as a formality. Reasoned responses to public comments are a required part of the report. Generic answers slow down the review and trigger questions from the expert commission.
    • Forgetting the validity periods. A scoping opinion lapses after 5 years, and a decision is declared void if the activity has not started within 7 years. Long projects should diary both dates.
    • Thin baseline data. If the current state of the environment is poorly described, the impact assessment will be weak too. This is the most common reason for requests for more information and delays.

    Practical checklist before you start a project

    1. Check the annexes. Find your activity in Annex I or II and compare it with the threshold (capacity, area, tonnage).
    2. Plan the calendar. A full EIA needs roughly 30 days for scoping and 85–90 days for the decision, plus time for baseline studies and report writing.
    3. Start baseline studies early. Some depend on the season, for example biodiversity surveys.
    4. Prepare for the public hearing. It is a formal stage, and your responses to comments become part of the report.
    5. Link the decision to other permits. Other licensing bodies must take the environmental decision into account; a construction permit, for example, often depends on it.
    6. Do not start work early. Article 5 prohibits the activity before the decision is issued.

    How Ecoman can help

    Together with partner experts, Ecoman prepares screening and scoping applications, the environmental impact assessment report and supporting documents, and helps clients obtain environmental permits and consents. For other permits, read our guide to environmental permits in Georgia. For the difference between an EIA, an EMP and an audit, see this article.

    Not sure whether your project falls under Annex I or II? Send us a short description and we will tell you which procedure applies.

    Information as of 22 November 2026. This article is not legal advice.

    Frequently Asked Questions

    The National Environmental Agency, a legal entity of public law within the Ministry of Environmental Protection and Agriculture. It also issues screening decisions and scoping opinions (Environmental Assessment Code, Article 3).

    Scoping ends with an opinion on day 26–30 after registration. After the EIA report is filed, the environmental decision is issued on day 85–90 after registration (day 51–55 under the accelerated procedure). Baseline studies and report writing come on top of these statutory periods.

    Annex I activities always need an EIA. Annex II activities go through screening first, and the Agency decides within 10–15 days of registration whether an EIA is needed.

    40 days from publication of the application (Article 12). The public hearing is held between day 25 and day 30 after publication. At scoping stage the comment period is 15 days.

    It is issued for an indefinite period, but the Agency declares it void if the activity has not started within 7 years. A scoping opinion lapses if no decision is obtained within 5 years.

    Sources

    1. Environmental Assessment Code of Georgia (No. 890-IIს), consolidated text (accessed 22 November 2026)
    2. Environmental Assessment Code of Georgia (English version) (accessed 22 November 2026)
    3. National Environmental Agency (accessed 22 November 2026)
    4. Ministry of Environmental Protection and Agriculture of Georgia (accessed 22 November 2026)

    How Ecoman can help

    Need Expert Environmental Consulting?

    Our team is ready to help with your compliance needs.

    Request Consultation

    Need Compliance Help?

    Get expert guidance on waste management regulations.