EIA Screening Application in Georgia: Documents and the 10–15 Day Timeline
You file a screening application if you plan an activity listed in Annex II of Georgia's Environmental Assessment Code, or want to change the operating conditions of an activity that already has an environmental decision. The application goes to the National Environmental Agency, which decides whether the project needs an EIA no earlier than day 10 and no later than day 15 after registration (Article 7(6)). The application must describe the activity and its characteristics, give the location as GIS coordinates with a shp file, and assess the likely impacts.
This article does not repeat the general overview of the Code (see Georgia's Environmental Assessment Code explained). It focuses on the screening stage only: how to tell whether you need an application, what goes into it and what happens day by day. We checked the Code on matsne.gov.ge on 26 November 2026; the latest consolidated text includes Law No. 1770 of 24 June 2026, published on 2 July.
Who needs a screening application
Under Article 5(1), Annex I activities always need an EIA. Annex II activities need one only if a screening decision says so. So the first question is always the same: which annex does your project fall under?
A screening application is required in two cases (Article 7(1)–(2)):
- A new Annex II activity, such as a small hydropower plant or an asphalt plant.
- A change in operating conditions of an activity that already holds an environmental decision (Article 5(12)). Here you may skip screening and file the application together with an EIA report on the change under Article 7¹; the decision then comes on day 40–45 after registration.
Where the same activity appears in both annexes with different thresholds, the larger scale belongs to Annex I and needs an EIA, while the smaller one belongs to Annex II and goes through screening (note to Annex II).
Annex II: common cases and thresholds
The table lists the Annex II items we see most often in business practice. It is not the full list; always check the exact wording in the Code.
| Item | Activity | Threshold |
|---|---|---|
| 1.1 | Using agricultural land for non-agricultural purposes | 10 ha or more |
| 2.1 | Open-pit extraction of solid minerals (except sand and gravel) | over 5 ha |
| 3.1 | Combustion installation for electricity generation | 2 MW or more |
| 3.5 | Storage of fossil fuel, oil products or gas | 100 m³ or more |
| 3.8 | Hydropower plant | 2–5 MW |
| 5.3 | Asphalt production | no threshold |
| 7.3 | Dairy production | over 20 t per day |
| 7.6 | Slaughterhouse | 300 or more animals per day |
| 9.2 | Urban development project (incl. shopping centre, car park for 1,000 cars) | built-up area over 10 ha |
| 10.2 | Recovery or disposal of hazardous waste | up to 10 t per year |
| 10.3 | Recovery/disposal of non-hazardous waste (except pre-treatment) | 10–100 t per year |
| 10.5 | Temporary storage facility for hazardous waste | over 10 t |
| 10.6 | Wastewater treatment plant | no threshold |
| 11.2 | Out-of-town holiday complex, incl. hotels | over 10 ha |
Annex II also covers, for example, housing for 500 or more cattle (1.5), wind power (3.9), industrial estates over 10 ha (9.1), sewer systems of 2 km or more (9.6) and sludge storage (10.7).
One detail matters for the waste sector: if screening releases a waste-related Annex II activity from EIA, that activity must still be registered under Article 26(1)(z) of the Waste Management Code. "No EIA" does not mean "no obligations".
What the screening application must contain
The application has to satisfy two laws. Article 78 of the General Administrative Code sets the elements of any application; Article 7(4) of the Environmental Assessment Code sets the specific content.
Checklist: formal part (General Administrative Code, Article 78)
- Name of the administrative body: the National Environmental Agency
- Applicant's identity and address (for a company: name, identification code, legal address)
- The request: a screening decision
- Date of filing and signature
- List of attached documents
Checklist: content (Environmental Assessment Code, Article 7(4))
- Short description of the activity: what, at what scale, for how long
- Characteristics: capacity, throughput, area, raw materials, water supply and wastewater, expected waste
- Location as GIS coordinates, with a shp file
- Likely impacts, addressed against the Article 7(6) criteria (see below)
- For operating-condition changes: the existing environmental decision, the planned changes and their likely impacts
From 1 September 2027, an operating-condition change that alters water abstraction from, or discharge into, a surface water body will also need the documents listed in Article 17 of the Law on Water Resources Management.
A gap we often see: coordinates appear only on a PDF map with no shp file, or the area in the text does not match the drawing. That is exactly the kind of "significant inconsistency" that can end the proceedings.
How the Agency decides
Article 7(6) sets three groups of criteria. A good application answers each one separately.
(a) Characteristics of the activity: scale; cumulative impact with existing or planned activities; use of natural resources (water, soil, land, biodiversity); waste generation; pollution and noise; risk of major accidents or disasters.
(b) Location: proximity to wetlands, the Black Sea coastal zone, forested areas dominated by Red List species, protected areas, settlements, cultural heritage sites, and landscape, recreational and forest zones.
(c) Nature of the impact: transboundary character, magnitude and complexity.
The Agency may use the guidance document "On environmental impact assessment" (Article 7(7)). Our advice: if the site is close to homes or a river, say so yourself and show what you will do to reduce the impact. Leaving a known risk out only makes the decision harder.
Unsure about your compliance obligations?
Our environmental consultants can assess your situation and provide a clear action plan.
Timeline, day by day
Days run from registration of the application. Under Article 79 of the General Administrative Code, an application is registered on the day it is received.
| Day | What happens | Basis |
|---|---|---|
| 0 | Application registered | General Administrative Code, Art. 79 |
| 1–3 | Agency publishes the application on the environmental information portal and the municipal notice board | Art. 7(5) |
| 7 days from publication | The public may submit comments | Art. 7(5) |
| Up to 8 days from publication | If information is missing or documents contain a significant inconsistency, the Agency terminates the proceedings | Art. 7(5¹) |
| 10–15 | Agency issues the screening decision | Art. 7(6) |
| 1 day after completion | Agency notifies the applicant | Art. 7(10) |
| 5 days after completion | Decision published on the portal and the municipal notice board | Art. 7(10) |
So with a complete and consistent application you get an answer within 15 days at most, about two weeks. If the proceedings are terminated, the clock starts again once you correct and refile. The only fast route is a complete, consistent package the first time.
What can follow screening
- No EIA needed. You may start, but technical regulations and environmental norms still apply (Article 7(8)). A waste management activity also needs registration (Waste Management Code, Article 26).
- EIA needed. Scoping starts: the scoping opinion comes on day 26–30 after registration, and after the EIA report is filed the environmental decision comes on day 85–90 (day 51–55 under the accelerated procedure). The EIA fee is 500 GEL (Article 11(5)). Until then the activity may not start (Article 5(2)).
- Refusal. The Agency refuses if the activity contradicts the law or a court decision, or the impact is unacceptable and cannot be mitigated (Article 14). A refusal can be appealed to a higher body or in court.
- Transboundary impact. If such a risk emerges, the Chapter V procedure applies (Article 7(11)).
When to skip screening
The Code gives two alternatives. You can file the screening and scoping applications together, with the documents required by Article 8 (Article 7(12)); if the Agency finds that an EIA is needed, the same decision starts scoping. Or you can go straight to scoping without screening (Article 7(13)).
When do we suggest this? When the project is close to an Annex I threshold, a protected area or a river, or when a lender will ask for a full assessment anyway. In those cases the two weeks "saved" by screening are often an illusion.
Common mistakes
- Wrong annex. Capacity or area is near the threshold and the expansion plan is left out. Cumulative impact is a criterion in its own right.
- A map without a shp file. The law asks for GIS coordinates with a shp file.
- Vague impact statements. "The impact is insignificant" is not an argument. Give data: distance to the nearest house, waste types and quantities, water source.
- A change without screening. Expanding an operating facility or changing its technology is a change of operating conditions and needs screening or the Article 7¹ procedure.
How Ecoman can help
Ecoman prepares the full screening package: the Annex II analysis, the impact description against the criteria, coordinates in shp format and communication with the Agency. If an EIA turns out to be needed, we also prepare the scoping and EIA reports. See Permits and consents and Environmental impact assessment. For an overview of other obligations, visit the compliance hub, or contact us to assess your project.
This article is for information only and is not legal advice.
Frequently Asked Questions
The National Environmental Agency decides no earlier than day 10 and no later than day 15 after the application is registered (Environmental Assessment Code, Article 7(6)). It notifies the applicant within 1 day and publishes the decision within 5 days.
Besides the standard details under Article 78 of the General Administrative Code, a short description of the activity, its characteristics, its location as GIS coordinates with a shp file, and the likely impacts assessed against the Article 7(6) criteria. For a change to an existing activity, also the current environmental decision and the planned changes.
Yes. If required information is missing or the documents contain a significant inconsistency, the Agency terminates the proceedings no later than 8 days after publishing the application (Article 7(5¹)). You then have to correct the package and file again.
Yes. You may file a scoping application directly (Article 7(13)) or file screening and scoping together (Article 7(12)). This often makes sense when the project is close to an Annex I threshold or a sensitive site.
No. You must still meet technical regulations and environmental norms (Article 7(8)). A waste-related Annex II activity released from EIA must also be registered under Article 26 of the Waste Management Code.
Sources
- Environmental Assessment Code of Georgia (No. 890-IIს), consolidated text (accessed 26 November 2026)
- Environmental Assessment Code of Georgia (English version) (accessed 26 November 2026)
- General Administrative Code of Georgia (accessed 26 November 2026)
- National Environmental Agency (accessed 26 November 2026)
- Ministry of Environmental Protection and Agriculture of Georgia (accessed 26 November 2026)
How Ecoman can help
Permits & Consents Support
Expert guidance and documentation support for environmental permits, project consents, and regulatory approvals.
Environmental Impact Assessment
Comprehensive Environmental Impact Assessments for development projects — delivered through our strategic partnership with Gergili LLC.
Need Expert Environmental Consulting?
Our team is ready to help with your compliance needs.
Request ConsultationNeed Compliance Help?
Get expert guidance on waste management regulations.