    A construction company needs a company waste management plan if it produces more than 400 tonnes of inert waste a year (1,000 tonnes for a natural person), more than 200 tonnes of other non-hazardous waste, or any amount of hazardous waste (Waste Management Code, Article 14(1)). The last condition is the one builders forget: an empty paint tin or an old battery is hazardous waste, and it can trigger the plan on its own.

    This article is about waste only. For the wider picture of a builder's environmental obligations, see our guide to environmental compliance for construction companies. Here we cover what counts as inert waste, how to count your tonnes, which site wastes hide behind hazardous codes and what fly-tipping costs. We checked the Code on matsne.gov.ge on 26 November 2026 (consolidated text, including Law No. 1552 of 29 April 2026).

    What counts as inert waste

    Under Article 3(ვ) of the Code, inert waste undergoes no significant physical, chemical or biological change: it does not dissolve, burn or otherwise react, it does not biodegrade, and it does not affect other material in a way that pollutes the environment or harms human health.

    In practice that means clean concrete, brick, tile and ceramic rubble, plus soil and stones. But "construction waste" and "inert waste" are not the same thing. A site also produces timber, metal, plastic, packaging, insulation and hazardous waste. None of these is inert, and different thresholds and rules apply to them.

    Excavated soil: when it is not waste

    The Code does not apply to uncontaminated soil and other naturally occurring material excavated during construction if it will clearly be used in its natural form on the same site, for that construction (Article 2(2)(დ)). Clean soil dug out of a foundation pit and used for backfilling on the same project stays out of your waste figures.

    Once soil leaves the site, or if it is contaminated, it is waste. Clean soil and stones take code 17 05 04; soil containing hazardous substances takes the mirror code 17 05 03*. Soil from a former industrial site or a petrol station should be tested before it goes anywhere.

    The 400 t threshold: how to count

    The threshold is annual and applies to the waste your company produces, not to one project. A company building several sites in a year adds up the inert waste from all of them. The Code counts in tonnes, so volumes recorded in cubic metres must be converted using real weighing data, not estimates.

    Worked example

    The numbers below are hypothetical and only show the method. Your own figures must come from weighbridge tickets and the receiving facility's acceptance documents.

    Waste streamCodeTruckloads per yearAverage weight (weighbridge ticket)Total, tonnes
    Concrete and brick rubble17 01 073012 t360
    Clean soil taken off site17 05 041014 t140
    Total inert waste500

    In this example a legal person exceeds 400 tonnes and needs a waste management plan. If the same site also collected a few empty paint tins that year, the plan would be required regardless of tonnage, because there is no minimum for hazardous waste.

    The method in four steps:

    1. Keep a weighbridge ticket or receiver's document for every load, showing the weight in tonnes.
    2. Split waste into streams and give each a code (see Georgian waste codes and classification).
    3. Add up all sites by calendar year.
    4. Count inert, other non-hazardous and hazardous waste separately, because each has its own threshold.

    If you have no weights, any factor you use to convert volume into tonnes must be justified and written down. A rough guess is a weak argument during an inspection.

    Which documents you need

    Obligations follow the thresholds:

    SituationObligationArticle
    More than 2 t a year of non-hazardous waste (excluding municipal waste) or any hazardous wasteWaste records and reporting; keep data for 3 years29
    More than 400 t inert (legal person), more than 200 t other non-hazardous, or any hazardousCompany waste management plan14
    Same conditions as for the planAppoint an environmental manager and notify the Ministry immediately15

    The plan must cover where waste comes from, its types, codes and quantities; prevention and recovery measures; how waste is separated, especially hazardous waste; temporary storage conditions; and treatment methods or the person who receives the waste (Article 14(1)). It is submitted to the Ministry and updated every 3 years, or sooner if waste types, quantities or treatment change significantly. Details: our waste management plan service.

    Who can take your waste: removal and receiving sites

    The waste producer must treat its waste itself or hand it to persons entitled to collect, transport and treat it (Article 7(4)). Collection and transport are subject to registration (Article 26(1)(ა)), and the carrier may only deliver waste to a facility that holds an environmental decision, an integrated environmental permit or a registration (Article 7(6)).

    The most important rule: your responsibility does not end when the truck leaves the gate. The original producer's responsibility lasts until the waste is fully recovered or disposed of (Article 7(5)). If a carrier dumps your rubble in a ravine, you will be asked questions too. Before removal, check the carrier's registration and the receiving facility's authorisation, and confirm local rules and accepted sites with the municipality.

    Landfill or reuse

    The Code divides landfills into three categories: hazardous, non-hazardous and inert (Article 21). Only inert waste may go to an inert landfill, so mixed site waste cannot be accepted there until it is sorted.

    Disposal is not the only route. Inert waste suitable for backfilling or construction need not go to landfill at all if, in agreement with a state or municipal body, it is used for backfilling or for construction foreseen by a project (Article 21(5¹)). This also follows the waste hierarchy, where disposal comes last. Get the agreement in writing and reflect it in your plan.

    Expert Support

    Unsure about your compliance obligations?

    Our environmental consultants can assess your situation and provide a clear action plan.

    Hazardous codes hiding on site

    Hazardous waste on a building site is usually small in volume, but it changes the legal picture completely:

    • 15 01 10* – packaging containing residues of hazardous substances: paint, solvent, varnish and sealant tins and cans.
    • 17 01 06* – mixtures of concrete, brick and tile contaminated with hazardous substances (the clean mirror entry is 17 01 07).
    • 17 05 03* – contaminated soil (the clean mirror entry is 17 05 04).
    • 16 06 01* – lead batteries from machinery and generators.
    • 20 01 21* – fluorescent tubes, especially in refurbishment and strip-out work.
    • Asbestos-containing waste – old corrugated roofing sheets and pipes found during demolition. It is hazardous and subject to special rules.

    With a mirror entry, if contamination is suspected, treat the waste as hazardous until shown otherwise. Hazardous waste must be collected separately in labelled containers and handed only to an authorised operator.

    Fines: the Article 32 ladder

    Fines for littering with construction or other inert waste depend on volume (Article 32):

    Volume dumpedLegal personNatural person
    Up to 1 m³GEL 2,000GEL 500
    1–10 m³GEL 3,000GEL 1,500
    10–50 m³GEL 15,000GEL 5,000
    50 m³ or moreGEL 30,000GEL 15,000

    Paying the fine does not end the matter: the offender must clean up the area immediately or within the reasonable deadline set (note to Article 32). A repeat offence doubles the fine (Article 47(2)), and the fine is also doubled for offences in protected areas (Article 47(3)).

    Other fines we see on sites:

    • handing non-hazardous waste to an unauthorised person – GEL 1,000; hazardous waste – GEL 2,000 (Article 35¹);
    • littering with hazardous waste or placing it outside its designated container – GEL 10,000 for a legal person (Article 36(2));
    • breaching asbestos-waste rules – GEL 3,000; breaching hazardous waste packaging and labelling rules – GEL 1,000 (Article 40¹).

    The full table is in our article on environmental fines for businesses in Georgia.

    Site checklist

    • Waste is split into streams: inert, metal, timber, packaging, hazardous.
    • Hazardous waste is kept separately in closed, labelled containers.
    • Every stream has a code; mirror entries have been checked.
    • A weighbridge ticket or receiver's document is kept for every load.
    • The carrier's registration and the receiving facility's authorisation have been checked.
    • Annual tonnes are totalled across all sites and compared with the thresholds.
    • Where required, the waste management plan is agreed and an environmental manager is appointed.
    • Reuse of clean soil on the same site, or backfilling with inert waste, is documented.

    How Ecoman can help

    Ecoman helps construction companies map their waste streams, assign codes, total annual tonnes, prepare and agree the company waste management plan, and provides an outsourced environmental manager. See our services for the construction sector or contact us and we will assess which obligations apply to you this year.

    This article is general information, not legal advice.

    Frequently Asked Questions

    When it produces more than 400 tonnes of inert waste a year (1,000 tonnes for a natural person), more than 200 tonnes of other non-hazardous waste, or any amount of hazardous waste (Waste Management Code, Article 14(1)). The thresholds are annual and cover all of the company's sites together.

    Not if it is uncontaminated and will clearly be used in its natural form on the same site, for the same construction (Article 2(2)(დ)). Soil taken off site is waste with code 17 05 04, or 17 05 03* if it contains hazardous substances.

    For a legal person GEL 2,000 up to 1 m³, GEL 3,000 for 1–10 m³, GEL 15,000 for 10–50 m³ and GEL 30,000 for 50 m³ or more (Article 32). The offender must also clean up the area, and a repeat offence doubles the fine.

    Yes. The original producer's responsibility lasts until the waste is fully recovered or disposed of (Article 7(5)). Use only registered carriers, check that the receiving facility is authorised, and keep weighbridge tickets and acceptance documents.

    Yes. Inert waste suitable for backfilling or construction may be used for backfilling or for construction foreseen by a project, in agreement with a state or municipal body, instead of going to landfill (Article 21(5¹)). Get the agreement in writing.

    Sources

    1. Waste Management Code of Georgia (No. 2994-რს), consolidated text (accessed 26 November 2026)
    2. Law No. 1552 amending the Waste Management Code (29 Apr 2026) (accessed 26 November 2026)
    3. Government Resolution No. 426 on the waste list and classification (accessed 26 November 2026)
    4. Ministry of Environmental Protection and Agriculture of Georgia (accessed 26 November 2026)

    How Ecoman can help

    Need Expert Environmental Consulting?

    Our team is ready to help with your compliance needs.

    Request Consultation

    Need Compliance Help?

    Get expert guidance on waste management regulations.